Hello All….. I’m building a 32Wx40L garage shop and i’m gonna pour a 6 inch concrete slab this year with radiant heat in the slab (PEX tubing) and the cement blocks are up for the outside forms my question is how do i screed across a 32 foot span i like to do it in one pour if i can any imput would be apprecated Thanks ……Chris…..
Discussion Forum
Discussion Forum
Up Next
Video Shorts
Featured Story
Listeners write in about power tool batteries, replacing sheathing behind brick, and rebuilding a pressure-treated deck.
Featured Video
How to Install Exterior Window TrimHighlights
"I have learned so much thanks to the searchable articles on the FHB website. I can confidently say that I expect to be a life-long subscriber." - M.K.
Replies
Lot of different ways. Are you planning to do this yourself without experienced help?
Welcome to the
Taunton University of Knowledge FHB Campus at Breaktime.
where ...
Excellence is its own reward!
i might get some help i dont know if there to experienced.....Chris.....
i might get
I suggest that you get lots of help!
oops must be a typo i'll be having at least 3 helpers looking for the best way to screed that length maby a power screed? mabey have to split it in half?.....Chris.....
sounds better!
You can place some intermitent interior screed boards that can be removed as you go in order to navigate that wide dimension. You will need lots of help with folk who know something about concrete work. It is not for the faint of heart.------WW 57
well when i built my house i had 3 helpers thats what i did even though it was smaller 24x36 thats a thought on how to do it im gonna need 2 truck (21yds) full that will give us time to work it out .... but whats good for a 16ft screed bar gotta get somthing better than a 2x4 if i can.....Chris.....
Have you ever done a wet screed?
k
p.s.- what's your main desire to do it all in one shot? delivery/ pump fees? speed?
Some of the best money I've spent was on a guy who did nothing but
horizontal concrete work. He had a lazer that he worked with as he went along. He also had control of the cement truck drivers. One driver even helped wheel barrow the cement. The drivers were very cooperative because he was known to them and there was a mutual reapect that you will not have. Hire someone who does it all the time and watch them work!
when 2 guys didn't show up and the concrete did... i placed a downramp (pit) for a loading dock.... alone.... about 12 yards if i remember right... the driver was cool... it was 100 degrees that day and he was nice enough to hose me off when i was about to pass out... he helped me screed off the rest and even stopped back by later that day to ck on me... told me he thought i was going to drop dead for a minute...
i was alot younger then ... have help that knows what they are doing... it's an expensive screw up if it gets away from you....
p
i find if you give tne drivers a tip thell be very helpfull.....Chris.....