FHB Logo Facebook LinkedIn Email Pinterest Twitter X Instagram Tiktok YouTube Plus Icon Close Icon Navigation Search Icon Navigation Search Icon Arrow Down Icon Video Guide Icon Article Guide Icon Modal Close Icon Guide Search Icon Skip to content
Subscribe
Log In
  • How-To
  • Design
  • Tools & Materials
  • Restoration
  • Videos
  • Blogs
  • Forum
  • Magazine
  • Members
  • FHB House
  • Podcast
Log In

Discussion Forum

Discussion Forum

New electrical supply

ozbuilder | Posted in Energy, Heating & Insulation on August 20, 2005 12:11pm

Hi everyone,
Iam upgrading the wiring in my house and am moving the location of my new circuit breaker panel. The wiring to the existing panel will not reach the location of the new panel, can I connect the old wiring to the new panel via a junction box in the ceiling?

Thanks,

Reply

Replies

  1. User avater
    IBEWChuck | Aug 20, 2005 12:18am | #1

    Are you referring to the load wires in the old panel? If so, they can be spliced in a box that remains accessible and extended to the new panel. The NEC limits the number of conductors in boxes based on the space[ in cubic inches] that is available. In other words, make sure your box is big enough or use several smaller boxes.

    1. ozbuilder | Aug 20, 2005 08:38pm | #9

      I am referring to the load wires in thye old panel. I want to splice them in a junction box in accessible ceiling space. Can anyone tell me the max. amount of wires allowed in a 666inch junction box.Thanks.

      1. User avater
        IBEWChuck | Aug 20, 2005 11:54pm | #10

        Assuming that your wires are all the same size[12 ga.], the code requires 2.25 cubic inches per conductor. The code counts each wire that enters the box and is spliced there as one conductor. So, a 12-2 romex entering and leaving would count as 4 conductors and need 9 cubic inches of space.[4X2.25=9] No allowances need to be made for locknuts or bushings. There is a special rule concerning equipment grounding conductors.I quote"Where one or more equipment grounding conductors enter a box, a single volume allowance in accordance with Table 314.16[B] shall be made based on the largest equipment grounding conductor or equipment bonding jumper present in the box"

         

        This means that if you are splicing two 12-2w/G cables, they are counted as 5 conductors for box fill calculation purposes.

        I hope you understand that there is not a short answer to your question. A 6x6x6 box would yield 216 cubic inches . Each #12 conductor needs 2.25 Cubic inches . If we assume that you are splicing cables with grounds to cables with grounds, each cable splice would consume 5X2.25 cubic inches for a total of 11.25 per splice. With a total volume available of 216, I calculate that you cuuld splice 19 cables in the box with a little space left over.

         

        I have assumed that you were splicing 12 gauge romex cables. If you are using 14 gauge wire each conductor requires 2.00 cubic inches of space.

         

        In the real world, you probably have a combination of sizes . Use good judgment and don't assume that the box is not full if you can cram more in it. Space is needed to disapate heat.

         

        Hope this helps. 

        By the way, my quotes are from the 2002 National Electrical Code, Article314

        1. ozbuilder | Aug 21, 2005 04:18am | #12

          Thanks,
          Your reply was very helpful - now I have one more question.
          My branch circits are original from 1956 and have two conductors and no ground, when i splice the circuits in the junction box is the lack of grounds on existing circuits (I am running alot of new circuits which will be grounded but will not be in the Junction box.) cause me any problems? What do I do with the grounds from the new cables in the J-Box? I will Be using 12ga. for my splices, I think that my existing circuits are mostly 12ga. In my native country of Australia it is legal to step down from 12 to 14ga. but not legal to step up so to speak, does that rule apply in the US?Thanks again.

          1. User avater
            IBEWChuck | Aug 21, 2005 04:57am | #13

            You will have no problems when you splice as long as you remember that the two wire cable served loads are not grounded. Tie the ground wires from your new cables to the metal j-boxes. Code requires all metallic parts of the system to be bonded to ground.

            You might consider that there is no time like the present to go ahead and run the grounded cable all the way to at least the first connection point on the circuit. Sometimes it will be quite a bit of trouble to fish the wires, but you will be grounded and have a better overall job.

            You can splice 14 to 12 . The important thing to remember is that 14 gauge wire needs to be on a breaker no larger than 15 amps. 20 amp breakers are ok for #12 wire. So, if you leave the new panel with #12 and splice it to #14 at a J-box,it must still be protected by a 15 amp breaker. Those circuits that are all #12 can go on the 20 amp breakers.

            Where are you at? Could you fill in your profile and let us know? I've tried to be pretty generic in my answers but local codes prevail.

            Chuck

             

      2. 4Lorn1 | Aug 21, 2005 02:51am | #11

        If you don't wish to keep the existing panel in place and use it as a junction box you can still use the enclosure as a junction box for connections. Mounted it anywhere you can get most of the cables to in good order. A single large box is faster than many small ones.You do need to install closures or plates to fill any holes opened up by removal or knockouts that are no longer used. In an attic or crawl space there isn't any need to make it look pretty. Steel 4x4 blank plates can be pressed into service to plate over large holes, like where the conduit coming from the meter was. TEK screws make it go quickly.Even a small panel, converted by removing the guts and screwing the cover closed has enough room to legally accommodate any likely number of conductors. Be sure to ground the box.Around most shops there is a collection of panel enclosures kept for this sort of situation. Sometimes obsolete or unavailable panel covers, replacement buss bars and insulators also.

  2. buildboy | Aug 20, 2005 12:38am | #2

    IBEWchuck is correct. However, if you are talking about the service wires (the ones from the pole to the main) I do not believe those can be spliced. Someone with more knowledge is sure to chime in...

  3. 4Lorn1 | Aug 20, 2005 01:46am | #3

    On the service side a conduit, sized for the conductor sizes and observing wire fill, run from the meter to the new location makes sense. Depending on the distance and local code and/or AHJ you may need to install a fused disconnect after the meter.

    Unless the distance is very small and the route well protected this is still a good idea IMHO. These conductors, after the meter but before the first point of disconnect, are unfused and so if shorted they have to blow clear. Even if the AHJ doesn't require it it is the way to go.

    On the branch circuit side typically the best solution is to convert the existing panel into a junction box and run conduit/s to the new location to get the existing circuits into the new panel. One honking big juction box is a lot easier than mounting a lot of small junction boxes.

    Watch the conduit fill and derate properly for the number of conductors. Also look at the ambient temperature where you run the conduit. Once the calculations are completed and one or two conduits run, you can use flex if it makes getting the conduit in more easily, pulling in wires and terminating is easy.

    Running cables is another way. You would need one cable per circuit but if the panel only has a couple of circuits and running a conduit is going to be a pain it may be the way to go.

    Helps if you keep the existing ground bar in the panel so you only need to run one ground. Usually a single #8 does it but go with the largest existing.

    The existing panel gets the door screwed shut and it can be painted over or otherwise disguised as long as it remains accessible without damaging finished surfaces or removing building structure.

    1. bosn | Aug 20, 2005 02:40am | #4

       The service entrance conductors from the meter won't reach or the branch circuit conductors from the panel to your house won't reach?  If the service entrance conductors won't reach you may have a question that can't be adequately answered with out seeing what you've got. 

      Here are some things to consider if in fact you are asking about the SEC's: 

      Ideally these wires would not be spliced. 

      They should be checked for proper size, as they might not even be the right size for your old service. 

      If they are aluminum they should probably be replaced.

      If you need to splice them, check your local codes.  Some jurisdictions have max distances from the meter to the main.

      The NEC specifies a max of ten feet of SEC the house that is unfused.

      You could put a main disconnect next to the meter or some where else to meet these above mentioned requirements and run fused(protected) conductors to the new panel location. If you do this you may want to as least consult with a local electrician or inspector.If you haven't drawn blood today, you haven't done anything.

      1. User avater
        BillHartmann | Aug 20, 2005 03:47am | #5

        "The NEC specifies a max of ten feet of SEC the house that is unfused."Is that new in the 2002 or 2005?All that I have seen is 230-70 (1999) that say accessible location either outside or inside "nearest" the point of entry.

        1. bosn | Aug 20, 2005 04:54am | #6

          Man, I can't find it.  I started out in the trade with the '96 NEC and a may be mixing up the NEC with our city code.  The requirement used to be that service entrance conductors could not pass through more than ten feet of raceway from the point they entered a building to the overcurrent device. 

          The current city code is that you are allowed no more then ten feet of conductor from the meter to the overcurrent device regardless of the location(inside or outside or combination.) This results in load centers being nearly back to back with the meter or the installation of a main disconnect near the meter and feeders run from the main to the load center.

          I have to admit this is safer than twenty feet of EMT with unprotected SEC's running across the basement ceiling.  I like the rule.  Guys used to get by the old rule by running the 20 feet of conduit on the outside of the house and poking through into the back of the load center. That was sooooo ugly.  Oh, and under the basement slab or through a crawl space was not considered "inside the house". 

          If this is in the code, or was,  would someone tell me so I don't continue to dwell on this.If you haven't drawn blood today, you haven't done anything.

          1. cap | Aug 20, 2005 09:06am | #7

            The "ten foot rule" isn't in the NEC, and never was.

            The issue is addressed by a local reqirement, or by policies set by the inspector.  Yea, I know, any requirement ought to be set fourth in written form, but often the inspector has to interpret the NEC.  With no local addendum to the NEC, it's up the the inspector to decide what "the point closest to where the service entrance conductors enter the building". 

            Cliff

          2. bosn | Aug 20, 2005 09:11am | #8

            Well if it isn't in the NEC, then it is in the Omaha code.  It is a very specific rule and it is in writing.  I just didn't remember where.If you haven't drawn blood today, you haven't done anything.

Log in or create an account to post a comment.

Sign up Log in

Become a member and get full access to FineHomebuilding.com

Video Shorts

Categories

  • Business
  • Code Questions
  • Construction Techniques
  • Energy, Heating & Insulation
  • General Discussion
  • Help/Work Wanted
  • Photo Gallery
  • Reader Classified
  • Tools for Home Building

Discussion Forum

Recent Posts and Replies

  • |
  • |
  • |
  • |
  • |
  • |
View More Create Post

Up Next

Video Shorts

Featured Story

Podcast Episode 689: Basement Garages, Compact ERVs, and Safer Paint Stripper

Listeners write in about ventilation and radon control and ask questions about tightening basement garages, ventilation solutions, and safer paint stripper.

Featured Video

Video: Build a Fireplace, Brick by Brick

Watch mason Mike Mehaffey construct a traditional-style fireplace that burns well and meets current building codes.

Related Stories

  • Design and Build a Pergola
  • Podcast Episode 689: Basement Garages, Compact ERVs, and Safer Paint Stripper
  • FHB Podcast Segment: Are Single-Room ERVs the Answer?
  • Fire-Resistant Landscaping and Home Design Details

Highlights

Fine Homebuilding All Access
Fine Homebuilding Podcast
Tool Tech
Plus, get an extra 20% off with code GIFT20

"I have learned so much thanks to the searchable articles on the FHB website. I can confidently say that I expect to be a life-long subscriber." - M.K.

Get home building tips, offers, and expert advice in your inbox

Signing you up...

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
See all newsletters
See all newsletters

Fine Homebuilding Magazine

  • Issue 332 - July 2025
    • Custom Built-ins With Job-Site Tools
    • Fight House Fires Through Design
    • Making the Move to Multifamily
  • Issue 331 - June 2025
    • A More Resilient Roof
    • Tool Test: You Need a Drywall Sander
    • Ducted vs. Ductless Heat Pumps
  • Issue 330 - April/May 2025
    • Deck Details for Durability
    • FAQs on HPWHs
    • 10 Tips for a Long-Lasting Paint Job
  • Issue 329 - Feb/Mar 2025
    • Smart Foundation for a Small Addition
    • A Kominka Comes West
    • Making Small Kitchens Work
  • Issue 328 - Dec/Jan 2024
    • How a Pro Replaces Columns
    • Passive House 3.0
    • Tool Test: Compact Line Lasers

Fine Home Building

Newsletter Sign-up

  • Fine Homebuilding

    Home building tips, offers, and expert advice in your inbox.

  • Green Building Advisor

    Building science and energy efficiency advice, plus special offers, in your inbox.

  • Old House Journal

    Repair, renovation, and restoration tips, plus special offers, in your inbox.

Signing you up...

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
See all newsletters

Follow

  • Fine Homebuilding

    Dig into cutting-edge approaches and decades of proven solutions with total access to our experts and tradespeople.

    Start Free Trial Now
    • Facebook
    • Instagram
    • X
    • LinkedIn
  • GBA Prime

    Get instant access to the latest developments in green building, research, and reports from the field.

    Start Free Trial Now
    • Facebook
    • YouTube
  • Old House Journal

    Learn how to restore, repair, update, and decorate your home.

    Subscribe Now
    • Facebook
    • Instagram
    • X
  • Fine Homebuilding

    Dig into cutting-edge approaches and decades of proven solutions with total access to our experts and tradespeople.

    Start Free Trial Now
    • Facebook
    • Instagram
    • X
    • LinkedIn
  • GBA Prime

    Get instant access to the latest developments in green building, research, and reports from the field.

    Start Free Trial Now
    • Facebook
    • YouTube
  • Old House Journal

    Learn how to restore, repair, update, and decorate your home.

    Subscribe Now
    • Facebook
    • Instagram
    • X

Membership & Magazine

  • Online Archive
  • Start Free Trial
  • Magazine Subscription
  • Magazine Renewal
  • Gift a Subscription
  • Customer Support
  • Privacy Preferences
  • About
  • Contact
  • Advertise
  • Careers
  • Terms of Use
  • Site Map
  • Do not sell or share my information
  • Privacy Policy
  • Accessibility
  • California Privacy Rights

© 2025 Active Interest Media. All rights reserved.

Fine Homebuilding receives a commission for items purchased through links on this site, including Amazon Associates and other affiliate advertising programs.

X
X
This is a dialog window which overlays the main content of the page. The modal window is a 'site map' of the most critical areas of the site. Pressing the Escape (ESC) button will close the modal and bring you back to where you were on the page.

Main Menu

  • How-To
  • Design
  • Tools & Materials
  • Video
  • Blogs
  • Forum
  • Project Guides
  • Reader Projects
  • Magazine
  • Members
  • FHB House

Podcasts

  • FHB Podcast
  • ProTalk

Webinars

  • Upcoming and On-Demand

Podcasts

  • FHB Podcast
  • ProTalk

Webinars

  • Upcoming and On-Demand

Popular Topics

  • Kitchens
  • Business
  • Bedrooms
  • Roofs
  • Architecture and Design
  • Green Building
  • Decks
  • Framing
  • Safety
  • Remodeling
  • Bathrooms
  • Windows
  • Tilework
  • Ceilings
  • HVAC

Magazine

  • Current Issue
  • Past Issues
  • Magazine Index
  • Subscribe
  • Online Archive
  • Author Guidelines

All Access

  • Member Home
  • Start Free Trial
  • Gift Membership

Online Learning

  • Courses
  • Project Guides
  • Reader Projects
  • Podcast

More

  • FHB Ambassadors
  • FHB House
  • Customer Support

Account

  • Log In
  • Join

Newsletter

Get home building tips, offers, and expert advice in your inbox

Signing you up...

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.
See all newsletters
See all newsletters

Follow

  • X
  • YouTube
  • instagram
  • facebook
  • pinterest
  • Tiktok

Join All Access

Become a member and get instant access to thousands of videos, how-tos, tool reviews, and design features.

Start Your Free Trial

Subscribe

FHB Magazine

Start your subscription today and save up to 70%

Subscribe

We hope you’ve enjoyed your free articles. To keep reading, become a member today.

Get complete site access to expert advice, how-to videos, Code Check, and more, plus the print magazine.

Start your FREE trial

Already a member? Log in