I am replacing an old, but sturdy oak floor with 3/4″ thick prefinished 4 1/4″ Maple flooring, about 1000 square feet. Would it be best to pull up the old floor or nail directly to the existing. My sub-floor is not plywood underlayment; it appears to be separate wood slats running perpendicular to the floor joists.
Discussion Forum
Discussion Forum
Up Next
Video Shorts
Featured Story
Fine Homebuilding's editorial director has some fun news to share.
Featured Video
Video: Build a Fireplace, Brick by BrickHighlights
"I have learned so much thanks to the searchable articles on the FHB website. I can confidently say that I expect to be a life-long subscriber." - M.K.
Replies
*
Larry,
Remove the old flooring. What's the sense adding another layer of 3/4" flooring on top of 3/4" flooring? You'd probably need to cut down any doors involved, bury the baseboard some more, and lose 3/4" in ceiling height. One sign of a better job is removing old, finish material before installing new, rather than just adding another layer of something. This goes along with many other aspects of remodeling, not just flooring.
Red dog
*
Thank you, red dog. That's what I'll do
*
I am replacing an old, but sturdy oak floor with 3/4" thick prefinished 4 1/4" Maple flooring, about 1000 square feet. Would it be best to pull up the old floor or nail directly to the existing. My sub-floor is not plywood underlayment; it appears to be separate wood slats running perpendicular to the floor joists.